2021/2022 Infrastructure and Paving Project Information

11/23/21

West I

  • Korff Plumbing wrapped up all Water Lateral replacement work.
  • Landscape restoration work and general clean-up will be on-going thru mid-December.

West II

  • Korff Plumbing wrapped up all Water Lateral replacement work.
  • Landscape restoration work and general cleanup will be on-going thru mid-December.
  • Minor Storm Sewer work will continue into December.
  • New roadways, new curbing and new driveway aprons will be constructed in 2022.

South I

  • The temporary water Lines have been removed.
  • Dorner Construction completed all the Water Main replacement work.
  • Van Rite Plumbing completed all the Water Lateral replacement work..
  • Minor Storm Sewer work will continue into December.
  • Landscape restoration work and general cleanup will be on-going thru mid-December.
  • New roadways, new curbing and new driveway aprons will be constructed in 2022.
10/22/21

West I

  • Korff Plumbing will be wrapping up all water lateral replacement work the week of November 1.
  • Landscape restoration, asphalt patching and concrete work will be on-going into late November.

West II

  • Korff Plumbing will be wrapping up all water lateral replacement work the week of November 1.
  • Landscape restoration, asphalt patching and concrete work will be on-going into late November.
  • Minor Storm Sewer work will continue into December.
  • New roadways, new curbing and new driveway aprons will be constructed in 2022.

South I

  • Temporary water lines were installed in late September.  These lines will be removed the week of November 15.
  • Water main replacement work and water lateral replacement work will continue thru the week of November 15.
  • At least three water main replacement crews will be on site to expedite the work.
  • Minor Storm Sewer work will continue into December.
  • New roadways, new curbing and new driveway aprons will be constructed in 2022.
10/3/21

West I

  • Korff Plumbing has completed water lateral replacement work south of Orchard Road.
  • After the Ryder Cup hiatus, water lateral replacement work will recommence on Orchard Road, Lincoln Circle and Upper Road in October.

West II

  • After the Ruder Cup pause, water lateral replacements will begin for those homes north of School Street. No water main work will occur in this area.
  • Minor Storm Sewer work, new roadways, new curbing and new driveway aprons will be constructed in 2022.

South I

  • Temporary water lines were installed in late September.
  • Water main replacement work and water lateral replacement work will commence in this area in early October.
  • At least two water main replacement crews will be on site to expedite the work.
  • Minor storm sewer work, new roadways, new curbing and new driveway aprons will be constructed in 2022.
9/3/21

West I

  • Korff Plumbing has completed water lateral replacement work south of Orchard Road. Restoration work still needs to be completed on a few homes on Church Street. The restoration work includes sidewalk installation, grading and seeding, new concrete curbing and permanent asphalt patching. This restoration work will be done the week of September 6th.
  • Water lateral replacement work will recommence on Orchard Road, Lincoln Circle and Upper Road after the Ryder Cup.

West II

  • Dorner is complete with the water main replacement.
  • All of the water service laterals have been replaced on School Street and areas south of School Street. Restoration is complete in this area as well.
  • After the Ryder Cup pause, water lateral replacements will begin for those homes north of School Street.
  • Minor storm sewer work, new roadways, new curbing and new driveway aprons will be constructed in 2022.

South I

  • Temporary water lines will be the first items to be installed in late September.
  • Water main replacement work and water lateral replacement work will commence in this area in early October.
  • At least two water main replacement crews will be on site to expedite the work.
  • Minor storm sewer work, new roadways, new curbing and new driveway aprons will be constructed in 2022.
8/9/21

West I

  • Korff Plumbing has completed lateral replacement for most of the areas south of School Street. This crew will be continue working north along Church Street in the next two weeks and onto Orchard Road, until pausing operations on August 27 for paving and land restoration crews to take over. The restoration work includes sidewalk installation, grading and seeding, new concrete curbing and permanent asphalt patching.
  • Work will recommence in this area after the Ryder Cup.

West II

  • Dorner Crew #1 and Van Rite Plumbing will continue replacing the water laterals on Hill Street and School Street.
  • Dorner Crew #2 continues on water main replacement on Valley Road and will complete water main and water lateral work in the next two weeks. This crew will then start working on storm sewer upgrades, as time allows prior to the Ryder Cup pause in late August.
  • After the Ryder Cup pause, water lateral replacements will begin for those homes in and adjacent to Upper Road.
  • Temporary water lines are being removed as the project progresses.
  • Lawn and asphalt restoration has begun.

South 1

  • Work will commence in this area in early October. Temporary water lines will be the first items to be installed.
7/13/21

West I

  • Korff Plumbing is complete with water lateral replacements for homes on South Road, Market Street and the south end of Church Street. This crew will complete Grafton Court this week and then work north on Church street towards School Street.
  • Landscape restoration and pavement patching will begin mid-August and end on September 3. The restoration work includes sidewalk concrete installation, grading and seeding adjacent to curbing and sidewalks, new concrete curbing and permanent asphalt patching.

West II

  • Dorner Crew #1 and Van Rite Plumbing are working on water laterals along Audubon Road and Green Tree Road.
  • Dorner Crew #2 is complete with water main replacement on Summit Road, Audubon Road, West Park Lane as well as the sanitary sewer on Green Tree Road. They will start water main replacement on Pine Tree Road, then on to Hill and School Streets.
  • The temporary water set up is still active on Green Tree Road, Pine Tree Road and Audubon Road. The next temporary water set ups will be on Hill Street and School Street.
  • Landscape restoration and pavement patching will begin in late July and end September 3. The restoration work includes sidewalk concrete repair, grading and seeding adjacent to curbing and sidewalks, temporary asphalt curbing, and temporary asphalt paving. Please be aware that in 2022, most of West II's roadways will be re-built inclusive of new curbing and driveway aprons.

South I

  • No activity is anticipated over the next few weeks.
6/28/21

West I:

  • Lead service lines have been replaced on South Road, East Park Lane and Market Street. Work is shifting north along Church Street and Grafton Court.
  • Restoration of roadways and private lawn areas in West I will be starting later in July.

West II:

  • Water Main replacement is complete on Summit Road and West Park Lane. Lead services lines are complete on Summit Road. Lead service line replacement on West Park lane will begin immediately.
  • Work is starting on the new sanitary sewer main on Green Tree Road.
  • Temporary water is being setup on Green Tree Road, Pine Tree Road and Audubon Road.
  • Temporary patching of roadways in West II will begin later this summer with some landscape restoration starting early August.

South I:

  • No activity is anticipated over the next few weeks in South I.
6/22/21

West I Update: Crews are well underway working on water lateral replacement in the West I area. Most of South Road, East Park Lane and Market Street is complete. Grafton Court and the south end of Church Street will be the focus the week of June 21st.

West II Update: The new water main is complete on Summit Road and West Park Lane. The next step is to install the permanent water lateral from the water main to your homes. Temporary water services for Pine Tree and Green Tree will be installed very soon. Additionally the Green Tree sanitary sewer replacement the week of June 21/28.

South I Update: No activity is anticipated over the next few weeks in South I.

5/25/21

The project has started. In West I, the water later installs have begun, and residents will be contacted by Korff Plumbing to schedule their lateral replacement. In West II, crews are looking to mobilize the first week of June to start setting up temporary water service and will begin installing water mains later that week. No South I activity is anticipated in the next few weeks.

Please be aware of construction crews and open excavations. Obey all traffic and sidewalk closures. Dust, noise and disruptions are part of construction, please be patient and courteous.

Please contact Brett Edgerle, 920-459-3881, at the Kohler Village Hall if you have any questions or concerns.